Tribhuvan
University
National
College of Engineering
Talchikhel, Lalitpur
Department of Civil
Engineering
A
Project
Report
On
PRE-FEASIBILITY
STUDY OF
MADME KHOLA II HYDROPOWER
PROJECT
(Course code:CE 755)
Submitted To
Department of Civil Engineering
In the Partial
Fulfillment of the Bachelor Degree of Civil Engineering
Submitted
By:
Bhava Raj
Joshi
072/BCE/420 SUPERVISOR:
Janak Raj
Joshi 072/BCE/436 Er. Aabishkar
Timilsina
Nanda Ram
Rokaya
072/BCE/444
Narayan
Budhathoki
072/BCE/445
Niraj
Bhandari (Sanki)
072/BCE/449
Pushkar
Raj Joshi
072/BCE/460
JULY 2019
COPYRIGHT
The author has agreed
that the library, Department of Civil Engineering, National College of
Engineering may make this thesis freely available for inspection. Moreover, the
author has agreed that permission for extensive copying or use of the material
of the project works for scholarly purpose may be granted by the supervisor of
the project work recorded herein or, in their absence, by the Head of the
Department of Civil Engineering, National College of Engineering. Copying or
publication or the other use of this thesis for financial gain without approval
of the Department of Civil Engineering, National College of Engineering and
author’s written permission is prohibited. Request for permission to copy or to
make any other use of the material in this thesis in whole or in part should be
addressed to:
Head of Department
Department of Civil Engineering
National College of Engineering
Talchikhel, Lalitpur, Nepal
NATIONAL COLLEGE OF ENGINEERING
(Affiliated
to Tribhuvan University)
Talchikhel,
Lalitpur, Nepal
DEPARTMENT OF CIVIL ENGINEERING
APPROVAL CERTIFICATE
The undersigned certify that they have
read, and recommended to the Institute of Engineering for acceptance, a project
entitled "Pre-Feasibility Study Of
Madme Khola Hydropower Project”, submitted by Bhava Raj Joshi(072/420),
Janak Raj Joshi(072/436),Nanda ram Rokaya (072/444),Narayan Budhathoki
(072/445),Niraj Bhandari sanki(072/449), Pushkar Raj Joshi(072/460) in partial
fulfillment of the requirements for the bachelor degree in Civil Engineering.
………………………………. ………………………
XYZ
Project Supervisor
External Examiner
……………………….
Head
of Department
Department
Of Civil Engineering
National
College Of Engineering
Talchikhel,Lalitpur
PREFACE
To introduce the students with the real
civil engineering practice and to give them confidence, ability to tackle
problems related to civil engineering and idea of practical working in
professional field with the application of theoretical knowledge gained during
the whole four years, there is a provision of project work in the syllabus of
TU.IOE on the final semester of bachelor’s degree program. This project
entitled “Pre-feasibility Study of Madme Khola hydropower project” is the one prepared by a
group of six students in partial fulfillment of the requirement for the
Bachelor’s degree in Civil Engineering subject entitled "PROJECT-II
(CE-755)" in Second Semester, Fourth Year.
Hydropower engineering includes great
diversified nature of work from meteorological analysis to geological study,
civil engineering structures, electromechanical installation, operation etc. In
order to complete this project, the period of one semester inclusive of the
regular classes and timely assessments is very difficult. However every effort
has been made to collect the most reliable data, past reports and relevant
design information.
From the very beginning of the project,
from the hydrological analysis to hydraulic design and then to
electro-mechanical components design every attempt have been made to cover all
the parts of a hydropower plant. This project group is sure that this report
will be beneficial for the detail investigation and design of the Madme Khola Hydropower
Project. The group will also be delighted for any feedback and suggestion to
upgrade this report.
JULY,
2019
ACKNOWLEDGEMENTS
It is our great
pleasure to submit this report on "Pre-feasibility Study on Madme Khola Hydro
Power Project" to the Department of Civil Engineering in partial
fulfillment of the requirement for the Bachelor's degree in Civil Engineering.
We would like to
express our sincere gratitude and thanks to our esteemed supervisor Er.
Aabishkar Timilsina for providing his valuable, remarkable support and kind
cooperation along with positive suggestions and guidance.
We would like to
extend our deep appreciation and acknowledgement to Project Coordinator Er.
Bikram Bhusal, Head of Department & Associate Professor Amrit Man Tuladhar and
others who are related to us for their kind support and precious knowledge with
cooperation.
Likewise, we would
like to extend special thanks to our admired friends in our class and others
for their remarkable help and kind support. We are also obliged to all our
family, friends and colleagues for their encouragements to complete this
Project Work.
Finally, last but not
the least, we express our sincere thanks to all of our well wishers.
Project Members
Bhava Raj
Joshi
072/BCE/420
Janak Raj
Joshi
072/BCE/436
Nanda Ram
Rokaya
072/BCE/444
Narayan
Budhathoki
072/BCE/445
Niraj
Bhandari (Sanki)
072/BCE/449
Pushkar
Raj Joshi
072/BCE/460
JULY,2019
SALIENT FEATURES
Name of the project: Madme
Khola Hydropower Project
Name of the river:
Madme Khola
Types of the scheme : ROR
Project location:
Namarjung Lower Municapility
District:
Kaski
Provience: Gandaki
Nearest town:
Sikhlesh
Access: Foot Trail
Latitude: 28°26'23" N to 28°25'26" N
Longitude:
84°09'50"E to 84°08'04" E
Weir Location: Namarjung Lower Municipality
Powerhouse Location: Namarjung Lower Municipality
Topo map details
HYDROLOGY
Catchment area: 36.33
km2
Catchment area above
5000 m 8.9
km2
Catchment area above 3000
m 25.91 km2
Catchment area below 3000 m 1.52
km2
TECHNICAL FEATURES
Design flow
2.81
m3/sec
Installed capacity
Head
gross head=128.7m
Net head 126.4
m
Head works weir=8.85m*2.6m (L*H)
Intake type Side
intake with 2 nos of opening (2m*1m) L*H
Stilling basin Length=11.682m
Gravel Trap Length=5m
Breadth=3m
Depth= 3m
Canal Length=2130.33
Width=1.5m
Depth=1.25m
Settling basin length=68.59 m
Number of chamber= 2 nos
Width
of each chamber= 6.42m
Forebay Length=25m
Width=
3m
Penstock Length=490m
Diameter=1.2m
Thickness=12mm
Powerhouse Length=18m
Width=
6m
Height=11.5m
LIST OF ABBREVIATIONS
Cm Centimeter
d water
depth
Dd Diameter of penstock after bifurcation
DHM Department of Hydrology and
Meteorology
Dia. Diameter
HSC Hydrological Similar Catchment EIA
Environmental Impact Assessment
Eq. Equation
f Frictional factor
FDC Flow Duration Curve
GT Gravel Trap
HFL High Flood Level
HGL Hydraulic Gradient Line
Ht Height
hw Static
Head in Penstock
hwm Water Hammer Pressure amsl Above Mean Sea Level
IRR Internal Rate of Return
MARR Minimum Attractive Rate of Return
Km Kilometer
KN Kilo Newton
Kv Kilo-volt
KVA
Kilo Volt Ampere
KW Kilo Watt
KWh Kilowatt hour
L length
Lb Length of penstock after
bifurcation
LT Low Tension
Ltd. Limited
m Meter
MCT Main
Central Trust
Table of Contents
COPYRIGHT……………………………………………………………………………………
PREFACE……………………………………………………………………………………….
ACKNOWLEDGEMENTS………………………………………………………
SALIENT FEATURE…………………………………………………………………………...
LIST OF
ABBREVIATIONS
2.1 REASON FOR
FOCUSING ON HYDROPOWER PROJECTS
2.2 HISTORY OF
HYDROPOWER DEVELOPMENT
2.3 HYDROPOWER
DEVELOPMENT IN NEPAL
3.1 HYDROPOWER
POTENTIAL OF NEPAL
3.2 HYDROPOWER
DEVELOPMENT OF NEPAL
3.5 LEGAL
PROVISIONS FOR INVESTMENT
4.2 Objective
of Hydrological Investigations
4.3 Drainage
Area Characteristics
4.4 Hydrological
and Meteorological Data
4.6 Long-term
Stream Flow Analysis
4.6.3 Methods
used for long term flow analysis
4.7.1 Importance
of Flood Flow Analysis
4.7.2 Method
for Flood Flow Analysis
4.7.2.2 For Gauged
River Basin (GRB):
4.7.3 Comparison of the flood of different method
5.2 Design
of hydraulic structures
5.5 ENERGY
DISSIPATION AT DOWNSTREAM
5.8.1 Hydraulic
Design of Trash racks
5.8.2 Shape
of Trash Rack Structure
5.8.6 Losses
at Trash Packs and intake openings
5.10.5 Components
of Settling Basin
6 POWER
OUTPUT AND ENERGY GENERATION
7 COST
ESTIMATES AND FINANCIAL ANALYSIS
7.2.1 Methods
of Financial Evaluation
7.2.2 Result
of Financial analysis
8 PROJECT
PLANNING AND SCHEDULING
8.4 TIME
MANAGEMENT IN PROJECT
9 CONCLUSION AND
RECOMMENDATION
LIST OF FIGURES
Fig 1: Location Of Proposed Site
Fig 2: Load Forecast By NEA
Fig 3: Rainfall
stations near the catchment
Fig 4: Madme Khola Hydropower Project Catchment Area
at Intake
Fig 5: Flow
Duration Curve
Fig 6: Ecological
Map of Nepal showing MIP regions
Fig 7: IDF curve of several locations of Nepal
Fig 8: Comparison
Of Flood Flow Analysis
Fig
09: Turbine selection graph
LIST OF TABLES
Table 1: Hydropower Potential of
Nepal GW
Table 2: Load forecast by NEA(year
2008)
Table 3: POWER DEVELOPMENT OF
NEPAL
Table 4: Value of constants for
WECS Method
Table5: MIP non dimensional regional hydrograph coefficients
Table
6: The value of
coefficient of runoff
Table
7: Comparasion of Flood Discharge
1
INTRODUCTION
1.1
GENERAL
Madme khola hydropower project is runoff type project. This
project will utilize a design
discharge of 2.81 m3/s and gross head of 128.4m.
Two Francis turbines have been considered for this project which will generate
the installed capacity of 3.14 MW. The project will be able to generate 1.815 GWh
during dry season, 11.25 GWh during the wet season and 13.10 Gwh of energy
annually. The present prefeasibility study has been carried out to establish
the technical viability of the project.
1.2
LOCATION
Madme khola Hydropower Project is located in Namarjung Rural Municapality of kaski district of the Gandaki province. The project area is located within the allocated license coordinate of Longitude 84°09'50"E to 84°08'04" E and Latitude 28°26'23" N to 28°25'26" N. The proposed headwork site and the powerhouse site of the project is located within Namarjung Rural Munacipality and at the side of Madi Nadi River.
Fig 1: Location Of Proposed
Site
1.3
ACCESS
The project Area is not totally accessible by
vehicular road. Till date there is no vehicular access to the proposed
headworks and powerhouse sites. A small way about 13 Km has to be constructed
from Sikles to get access to the powerhouse site and Headworks. During the
construction of the project, a new road has to be constructed to connect the
proposed headwork and powerhouse site by vehicle.
1.4
GEOLOGY OF PROJECT SITE
Madme Khola Project site is located in Himalayan zone.
Geology of the project site is sound with respect to surface geological study.
Surface geology of the site define the design type, quality etc. of any
structure on or below the surface of earth. For the detailed study of the
project geology of the project site should be identified.
1.5
OBJECTIVE OF STUDY
The objectives of the pre-feasibility study are to:
v
Find a suitable
project site
v
To apply the
theoretical knowledge in practice.
v
To be familiar with
the analysis and design of hydropower project.
v
To know the method of designing of various
components of a hydropower project.
v
To be familiar with estimating
costing and financial analysis.
v
To know and face the
practical problem in designing and undertaking such project
v To gain the skill of
designing of hydropower project.
v To analyze the project
whether financially justified or not. To prepare a report of hydropower
project.
1.6
STUDY
EXECUTION
A desk study was carried out based on the topographical maps and
previous data's. Hydrological analysis was then carried out based on daily flow
data available from Madi Nadi River provided from Department of Hydrology and
Meteorology (DHM) of Nepal. Based on the design flow estimated from hydrology
analysis, the project has been designed.
2
BACKGROUND
2.1
REASON
FOR FOCUSING ON HYDROPOWER PROJECTS
At
every course of action, technology is developed as per human needs which have
both positive as well as negative impacts. The rate of development of world is
increasing day by day and it has pronounced negative impacts such as depletion
of natural resources, environmental degradation, etc. The scenario of energy
consumption is at the increasing rate. This causes depletion of non-renewable
and exhaustive sources of energy, sustainable development which means that our
children should get at least as much resource that we are consuming at present.
So, energy consumers should be keen on using of non exhaustive and renewable
sources of energy. Hydropower, one of the most reliable and common renewable
sources of energy is abundantly available in the hilly regions like Nepal.
Again, hydraulic conveyance circuit can be beneficial for multipurpose use
(irrigation, water supply, etc.). Hydropower production does not consume water,
so it is considered as renewable source of energy.
Due
to presence of abundant water resources and potential hydropower sites, there
is huge possibility of hydropower power production in Nepal. Large projects
involve huge amount of funds and the development period is also long. Hence,
activities regarding development of small hydropower projects are accelerating
these days which is technically, financially and socially sustainable at the
present scenario.
2.2
HISTORY OF HYDROPOWER
DEVELOPMENT
Use of energy generated from water has
been started since the very beginning of human civilization. Michael Faraday
demonstrated that mechanical energy could be converted into electrical energy
and vice-versa, in 1831, development and use of electrical energy began gaining
momentum after 1890. By 1900, hydropower plants had become a common source of
obtaining electricity. In the early 19th century. progress in the hydropower
development was slow because of less efficiency in power transmission over the
long distance. The pace of hydropower development increased dramatically after
1930. United States made a policy to invest in water based projects to create
jobs for unemployed and to stimulate Financial recovery in the country when it
faced severe Financial hardship in 1929. In the former SovietUnion, hydropower
was considered synonymous with industrialization and Financial prosperity after
1920.
After
2nd world war, leaders of African and Asian nations has replicated
the western US model to meet energy and water needs of their own countries and
many large scale hydropower projects were built in India, Pakistan and Egypt
between 1950 and 1980.
None
of the projects in US, former Soviet Union and India had the objective of
exporting energy to its neighboring to earn revenue for the country. In recent
decades, the concept of production of electrical energy has been changed. Now,
has been traded between two or more nations after agreement upon certain terms
of trade. Exporting electricity to a neighboring country to earn revenue for
the government is one of the stated objectives of developing large-scale
hydropower projects in Nepal.
2.3
HYDROPOWER
DEVELOPMENT IN NEPAL
Nepal
has a huge hydropower potential. The average annual precipitation is about
1700mm (80% of which occurs during monsoon season from June to September). The
total annual average runoff from Nepal's 6000 rivers is over 200 billion m .In
face, the perennial rivers and the steep gradient of the country's topography
provide ideal conditions for the development of some of the largest
hydroelectric project in Nepal. The water storage potential of 88 billion m^3
and the diversified climate and the physical environment are the notable
factors that account for large hydropower generation in Nepal. The distance between
the agnatic plain at about 70 m from MSL to the Mt. Everest at 8848m from MSL
is only about 170 km, and the steep slope accounts for high head for hydropower
generation. Nepal's theoretical hydropower potential is estimated at 83,000 MW
(Dr. Hari Man Shrestha) and out of this gross potential, 44,000 MW has been
found technical feasible. At present, 93 dam's sites have been identified and
66 of these are found financially feasible with total generation capacity of
about 42,000MW. However, the present situation is that Nepal has developed only
approximate 1020.625MW of hydropower. Therefore, bulk of the Financial feasible
generation has not been realized yet. Besides, the multipurpose, properly
planned and managed, development of its rivers. If properly planned and
managed, development of Nepal's storage potential could yield tremendous
benefits to Nepal and its neighbors in the form of hydropower generation, flood
control during the monsoon and flow augmentation for downstream irrigation.
Hydropower
currently provides almost all of Nepal's electric power. Nepal's topography
gives enormous scope for the development of hydro-electricity, which probably
provides the only realistic basis for its further financial development. Small
scale hydro plants are the most viable option for rural electrification. Large
projects, however, in view of Nepal's limited financial resources, would
probably require power export contracts with India as prerequisite. Energy through
hydropower contributes to 95 percent of total electricity generation in Nepal.
Until 2018, only 2.43 percent of the calculated potential 42000 MW had been
realized. The benefit of the large scale hydropower has not been flowed to the
majority of the people in Nepal, 90 percent on who lead in agriculture life.
According to the population census of 2016, 90.7 percent of the people of Nepal
have access to electricity, and are mostly urban.
First
hydropower plant developed in Nepal was Pharping Hydropower station (500KW) IN
1911. But the progressive development was noticed only after the Sundarijal
(600KW) and Panauti (2400KW) Hydropower Station came into operation after long
interval of 23 and 29 years.
The
completion of Dhankuta Hydropower station (240 KW) in 1971 was regarded as the
bench mark of small hydropower development of Nepal. The establishment of small
hydropower development board in 1975 was another milestone under which several
small hydro schemes such as Jhupra (345 KW), Doti (200KW), Jhumal (200 KW) etc.
were made during 1975 to 1985. Nepal Electric Authority (NEA), established
1975, responsible for generation, transmissions and distribution of electric
power brought the revolution in hydropower development. Many potential sites
for hydropower generation had identified by private consultancies and companies
in collaboration with NEA.
Prior
to 1960, all the hydropower stations were constructed through grant aid from
friendly countries like the USSR (Panauti), India (Trisuli, Devighat, Gandak,
Suajpura-Koshi), China (Sunkoshi), and Germany (Madhya- Marshyandi). Since
1970. Hydropower development took a new turn with the availability of bilateral
and multilateral funding sources. The major donor countries in the period were
Japan, Germany, Norway, South Korea, Canada, Finland, Denmark, Sweden and USA.
The financial leading agencies were the World Bank, Asian development bank
(ADB),Japanese bank of international cooperation (JBIC), Saudi fund for
development,Kuwait fund and others.
From
1990s, subsequent to the adoption of the policy of financial liberalization,
hydropower development took yet another turn with the private sector entering
the arena. After formulating Hydropower Development Policy-1992 by the
government of Nepal, many private sectors are involving towards power
development. In order to encompass projects of various scales intended
for
domestic consumption as well as to export hydropower, the former policy was
replaced by the Hydropower Development Policy 2001 to provide further impetus
to active participation of private sectors.
Development
of hydropower in Nepal is a very complex task as it faces numerous challenges
and obstacles. Some of the factors attributed to the low level of hydropower
development are lack of capital, high cost of technology, political instability
and lower load factors due to lower level of productive end-use and high
technical and non-technical losses.
3
POWER
MARKET IN NEPAL
3.1
HYDROPOWER
POTENTIAL OF NEPAL
Nepal
has a total hydropower potential of 83,000MW out of which about 42,000MW is
assessed to be financially feasible (Dr. Hari Man Shrestha).
Table
1: Hydropower Potential of Nepal GW (Source: Water Resources of Nepal, CK
Sharma)
River Basin |
Theoretical |
Technical |
Financial |
Saptakoshi |
22.35 |
11.40 |
10.48 |
Karnali |
34.60 |
24.36 |
24.00 |
Gandaki |
17.92 |
6.73 |
6.27 |
Mahakali |
1.58 |
1.13 |
1.13 |
Others |
3.07 |
0.98 |
0.98 |
Total |
83.29 |
44.60 |
42.15 |
About
6000 big and small rivers have been identified in Nepal carrying about 179
cubic million meters of water run-off annually. All the major river basins,
except those of the southern rivers originated in Himalayan or Tibetan Plateau.
Major achievements in the financial development of Nepal could be achieved
through power harnessing of the vast water resource.
3.2
HYDROPOWER
DEVELOPMENT OF NEPAL
Although the first power plant has been
constructed in Nepal 1911, expansion of more hydropower plants has been slow.
Then other hydropower plants followed after 23 and 29yrs after the commission
of the first one. The subsequent hydro projects came into service in a
reasonable short interval. NEA (Nepal Electricity Authority) established 1985
is responsible for generation, transmission and distribution of electric power
in Nepal.
NEA
has classified the hydroelectric Projects into the following five groups:
1.
Micro Hydro: Less than 100KW
2.
Mini hydro: 100KW to 1MW
3.
Small hydro: 1 to 10MW
4.
Medium hydro: 10 to 300MW
5.
Large hydro: more than 300MW
3.3
POWER
DEMAND AND SUPPLY
Power
is one of the main fundamental requirements for the modern and its demand is
very high for the industrial development and domestic use. For the developing
country Like Nepal is highly needed to improve the industrial sector which will
help to reduce poverty through improvement of the economy and employments
creation. According the NEA, energy demand forecast for the coming years is
shown in Figure below.
According
to the NEA annual report 2018, the total installed capacity in Nepal
Electricity Authority's (NEA) Integrated system is 1074.135 MW including the
1020.625 MW hydro plants ,Total Thermal Power(NEA) 53.410 MW and total Solar
Power 0.1MW.Currently, the peak demand is about1300 MW and the deficit is 225MW
and the country is facing acute shortage of energy especially during the dry
season.
SOME UNDER CONSTRUCTION POWER PROJECT
Arun III -900 MW Khani khola -30MW
Upper Tamakoshi
-456 MW Kulikhani III -14 MW
Rasuwagadhi
-111 MW
Mistri Khola -42 MW
Middle Bhotekosi
-102 MW Gamgadhi - 0.8 MW
Lower Sanjeen
-42.5 Iwa Khola -9.9 MW
Lower Modi
-20 MW
Upper Sanjeen
-14.8 MW
Rudhi Khola
-8.8 MW
Upper Naugad Gad
-8 MW
3.4
POWER DISTRIBUTION PLAN
The need to extend distribution over the country is reflected from the
fact that 85% population of the country is not getting electricity as a source
of energy. So, the distribution of electricity should be done strategically.
NEA has taken systematic studies of carrying out rural electrification and
distribution system reinforcement (DSR) feasibility on district-wise basis. NEA
intends to undertake these works with multi-source financing. Also, Nepal
Government contributes to rural electrification scheme on an annual basis with
an increasing magnitude in the year, 1999/2000, outlay being approximately 4.5
million US dollar. NEA and Nepal Government are jointly working for the
electrification of rural areas. To cope with this objective, micro and small
hydropower are the better options in the present scenario.
3.5
LEGAL PROVISIONS FOR INVESTMENT
Hydropower
industry is one of the major industries with wider scope in Nepal. For an
industry to prosper there should be support of government policies and legal provisions.
Only the potential cannot do the development of a nation if the policies cannot
be harnessed. Clearly defined conditions and attractive policy are always
essential to harness the innumerous resources. Realizing this fact, Nepal
Government has developed certain policies.
4
HYDROLOGY
4.1
INTRODUCTION
Hydrology is described as the science associated with the
occurrence, circulation and distribution of water on land, atmosphere and
underground; it also studies about the physical and chemical properties of
water and their reaction with the environment. The various processes involved
are precipitation, evaporation, infiltration, runoff, groundwater flow and
stream flow.
Since it is evident that a hydropower project is
fundamentally dependent on the hydrological inputs of that location, it becomes
necessary that the hydrological processes and characteristics required for the
project such as:-precipitation, runoff, stream flow, area of catchment in a
distinctive zone i.e. snow clad zone, vegetation cover, slope of land in
catchment etc. be prudently studied and analyzed. The design of a stable,
economic and deft functioning project is excessively reliant on the water
characteristics or the flow. The installed capacity at which the project is
understood to run for the entirety of the project span, bases on the mean
monthly flow whereas the physical aspects of project rely on the flood flow
analysis of the river. Here in our study as per the location, the type of river
(gauged or ungauged) and data available, we carried out some hydrological
calculations based on the following items such as:-stream flow, precipitation
data, area of catchments, land slope, ground cover coefficients etc.
4.2
Objective of Hydrological Investigations
Hydrological investigations performed for design of
headworks of run-of-river hydropower projects were aimed at achieving the
following objectives:
Providing input for the selection of return period for
inflow design flood, construction diversion flood and low flows.
Developing flow duration curves mean monthly hydrographs,
rating curves and water surface profiles at the headworks.
4.3
Drainage Area Characteristics
Information on the physiographic characteristics of the
drainage area, such as the latitude, altitude, area and shape of the basin,
length of main channel, gradient of channel and basin, etc., were derived from
topographic maps 1:50,000 (sheet No.2884 09) published by the Survey Department, GoN. These
data were used in the calculation of various hydrological parameters.
4.4
Hydrological and Meteorological Data
Hydro-meteorological data from the hydrometric and
meteorological stations existing in and around the river basin were obtained
from publications of the Department of Hydrology and Meteorology (DHM), GoN.
Source:
Google Earth
Fig 3:
Rainfall stations near the catchment
4.5
THE CATCHMENT
Madme Khola is the tributary of Madi Nadi
river and has catchment area of 36.33 km2.
The catchment area above permanent snow line
(EL.5000 m) about is 8.9 km2 and the catchment area above(EL.3000)
is 25.91 km2 .the upper part of the catchment is confined by
mountains.
The upper part of the catchment has snow,
which contribute to sustained flow during the dry season.The stiffness of the
topography of the area contributes not only to rapid flooding but also to a
high erosion rate and high sediment carrying capacity.
Fig 4:
Madme Khola Hydropower Project Catchment Area at Intake
4.6
Long-term Stream Flow Analysis
The long term flow analysis is carried out to obtain the
average discharge that will be available for us in the river for the useful
life of the project. This analysis will provide us with the average monthly
discharge and then these values can be used to obtain the flow duration curve
and design discharge of the project.
4.6.1
Importance
The long term flow analysis is very critical as it will provide
the design discharge of the project. The optimization of the installed capacity
of any hydropower project is done with the help of long term long term stream
flow data. These data are used to formulate the Flow Duration Curve, and the discharge exceeding certain percentage
of time is used for the optimization between the cost of the project and the
benefit from the power revenue. This eventually leads the healthy economics of
the project.
4.6.2
Flow Duration Curve
The flow-duration curve is a cumulative frequency curve that
show the percent of time specified discharges were equaled or exceeded during a
given period. It combines in one curve the flow characteristics of a stream
throughout the range of discharge, without regard to the sequence of
occurrence. If the period upon which the curve is based represents the
long-term flow of a stream, the curve may be used to predict the distribution
of future flows for water-power, water-supply, and pollution studies.
It is simply obtained by plotting the discharge as ordinate
and the percentage of time duration for which that magnitude or more is
available as abscissa. In hydropower project, flow duration curves are widely
used to assess the dependability of the discharge. Basically these are used in
assessing the dependable power in runoff river plant with or without pondage.
Fig 5: Flow Duration
Curve
4.6.3
Methods used for long term flow analysis
•
Catchment Area Ratio Method
• WECS/DHM
Method (WECS/DHM, 1990)
• MIP
Method
4.6.3.1
Catchment Area Ratio Method
If two basins are hydro-meteorologically similar, data
extension may accomplished simply by multiplying the available long-term data
at the HSC with the ratio of the basin areas of the base station (proposed site
under study) and the index (HSC) station. More accurate results were obtained
using Dicken‟s flood formula,
Qb=Qi*()3/4Where,Qb and Qi are the discharges at the base and index stations,
respectively, and Ab and Ai are the corresponding
basin areas.
WECS/DHM Method
This method is developed for predicting the river flows for
catchment areas larger than 100 sq km. of ungauged rivers based on hydrological
theories, empirical equations and statistics. In this method, the total
catchment area, areas between 5000 m to 3000 m are required as input. Flow
contribution per unit area for 5000 m to 3000 m and from lower elevations i.e.
below 3000 m is assumed to be in different proportion during flood. However,
for long term average monthly flows all areas below 5000 m are assumed to
contribute flows equally per sq. km. area. The average monthly flows can be
calculated by the equation:
Q mean= C×(Total basin area)A1×(Basin
area below 5000m+1)A2×(Monsoon wetness index)A3
Where, C, A1, A2, A3 are constants derived from the
regression analysis.
A is the catchment area in Km2.
Q is discharge in m3/sec
Table 4: Value of constants for WECS Method
Month |
C |
A1 |
A2 |
A3 |
January |
0.0142 |
0.0000 |
0.9777 |
0.0000 |
February |
0.0122 |
0.0000 |
0.9766 |
0.0000 |
March |
0.0100 |
0.0000 |
0.9948 |
0.0000 |
April |
0.0080 |
0.0000 |
1.0435 |
0.0000 |
May |
0.0084 |
0.0000 |
1.0898 |
0.0000 |
June |
0.0069 |
0.9968 |
0.0000 |
0.2610 |
July |
0.0212 |
0.0000 |
1.0093 |
0.2523 |
August |
0.0255 |
0.0000 |
0.9963 |
0.2620 |
September |
0.0168 |
0.0000 |
0.9894 |
0.2878 |
October |
0.0097 |
0.0000 |
0.9880 |
0.2508 |
November |
0.0018 |
0.9605 |
0.0000 |
0.3910 |
December |
0.0015 |
0.9536 |
0.0000 |
0.3607 |
The values of the constants
for different months are different. The Monsoon Wetness Index for the catchment
area is taken from Isohyetal map of Nepal.
4.6.3.2
MIP Method
The MIP method presents a technique for estimating the
distribution of monthly flows throughout a year for ungauged locations. For
application to ungauged sites, it is necessary to obtain one flow measurement
in the low flow period from November to April.
In MIP Method, Nepal has been divided into seven Zones. Once
the catchment area of the scheme, one flow measurement in the low flow period
and the hydrological zone is identified, long-term average monthly flows can be
determined by multiplying the unit hydrograph (of concerned region) with the
measured catchment area.
Hydrological zone can be identified based on the location of
the scheme in the hydrological zoned map of Nepal.
For catchment area less than 100 km2, MIP method
is used for better results,
If the measured date is on 15th of the particular
month, the coefficient given in the table is directly used. For other date
measurement, coefficient for that date is found by interpolation.
April flow = * Measured discharge
Monthly flow =April flow × Monthly coefficient
Fig 6:
Ecological Map of Nepal showing MIP regions
Table 5: MIP non
dimensional regional hydrograph coefficients
Month/Region
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
Jan |
2.4 |
2.24 |
2.71 |
2.59 |
2.42 |
2.03 |
3.3 |
Feb |
1.8 |
1.7 |
1.88 |
1.88 |
1.82 |
1.62 |
2.2 |
Mar |
1.3 |
1.33 |
1.38 |
1.38 |
1.36 |
1.27 |
1.4 |
Apr |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
May |
2.6 |
1.21 |
1.88 |
2.19 |
0.91 |
2.57 |
3.5 |
Jun |
6 |
7.27 |
3.13 |
3.75 |
2.73 |
6.08 |
6 |
Jul |
14.5 |
18.18 |
13.54 |
6.89 |
11.21 |
24.32 |
14 |
Aug |
25 |
27.27 |
25 |
27.27 |
13.94 |
33.78 |
35 |
Sept |
16.5 |
20.91 |
20.83 |
20.91 |
10 |
27.03 |
24 |
Oct |
8 |
9.09 |
10.42 |
6.89 |
6.52 |
6.08 |
12 |
Nov |
4.1 |
3.94 |
5 |
5 |
4.55 |
3.38 |
7.5 |
Dec |
3.1 |
3.03 |
3.75 |
3.44 |
3.33 |
2.57 |
5 |
4.7
Flood Flow Analysis
In hydropower projects, high floods are required to be
computed for designing the headwork structures as well as the powerhouse
complex. Flood hydrology is analysed in two parts – design floods for the
design of headworks and other hydraulic structures and construction floods for
diversion of flood during construction period.
Finding out of the design flood in different return period
are very important for the evaluation and design of any water resource projects
such as design of hydropower, design of culverts and bridges, etc. The flood
flow analysis is carried out to obtain the worst flood that can occur during
the 100 years time so that we can design the structures accordingly for their
safety and safety of the whole project.
4.7.1
Importance of Flood Flow Analysis
The flood flow analysis is of supreme importance as failure
to predict the flood flow correctly may cause the immature demise of the whole
project due to unforeseen flood. Reliable flood estimates are essential as the
viability of a project depends on the economy of hydraulic structures.
4.7.2
Method for Flood Flow Analysis
For
Ungauged Basin:
1.Regional Methods
• WECS/DHM
• Rational
Method
2.Empirical Method
• Snyder‟s
Method
• B.
D. Richard‟s Method
• Modified
Dicken‟s Method
• Fuller
Method
For Gauged Basin
• Gumbel
Method
4.7.2.1
For
Ungauged basins
4.7.2.1.1 Regional Methods
Regional formulae are based on statistical
correlation of the observed peak and important catchment properties. They are
made by the Departments or organizations based on the data of area of
catchment, slope, coefficients of land cover etc. These formulae are best
exemplified on the hydrologically homogenous areas or catchments.
Below are some of the rational methods used to
compute the flood flow :
4.7.2.1.1.1
WECS/DHM method (Water and Energy Commission
Secretariats)
The WECS/DHM method (WECS/DHM, 1990) may be used for flood
prediction for small hydropower project located in unguaged basins of Nepal.
Using this method, 2-year (medium flood) and 100-year floods for maximum daily
and maximum instantaneous flood peaks shall be computed from regression
equations of the form
Where -the discharge in m3/s,
Subscriptly or an instantaneous flood
peak, subscript
is either a 2 year or a 100 year return
period.
.
= 14.63 for 100 year
or 2 year
= 0.7342 for 100 year
A3000= Basin area km2 below 3000 m
elevation
For other return periods
QT= exp(lnQ2+S)
Where,
QT= Other flood for T year return
period m3/s
S=standard normal variate,
4.7.2.1.1.2 Rational Method
Rational method is commonly used method for computing peak
discharge for small basins. The idea behind this method is that if a rainfall
of intensity „i‟ begins instantaneously and continues indefinitely, the rate of
runoff will increase until the time of concentration (tc), when all
of the basin is contributing to flow at the outlet. After tc, runoff
becomes constant for the period of rainfall excess (t- tc). Rational
method is useful for small catchments upto 50 sq. km.
The peak discharge is given by:
Qp= (CiA)/3.6
Where
Qp= Peak flood discharge (m3/s)
C = Co efficient of Runoff (value ranges in between 0 and 1)
i = Intensity of rainfall (in mm/hr)
A =Area of catchment (in km2)
Assumptions:
-The computed peak rate of runoff at the outlet point is a
function of the average rainfall rate
during tc.
- tcemployed is the time for runoff to become
established and flow from the most remote part of the basin to the outlet.
-Rainfall intensity is constant throughout the storm
duration.
Table 6: The value of coefficient of runoff
Types of
basin |
C |
Rocky and permeable |
0.8 – 1.0 |
Slightly impermeable, bare |
0.6 – 0.8 |
Cultivated or covered with vegetation |
0.4 – 0.6 |
Cultivated absorbent soil |
0.3 – 0.4 |
Sandy soil |
0.2 – 0.3 |
Heavy forest |
0.1 – 0.3 |
Fig 7: IDF curve of
several locations of Nepal
4.7.2.1.2 Empirical Methods
Empirical formulae shall be used only when a more accurate
method for flood prediction cannot be applied because of lack of data. For
flood prediction in ungauged basins of Nepal, the empirical formulae discussed
in the following sections may be used with great caution and proper
justification. Empirical formulae can be epitomized as Qp=f(A)
Below are some of the empirical methods used for the
computation of flood flow:
4.7.2.1.2.1
Snyder’s Method
Snyder‟s method was used for flood flow estimation by
deriving a synthetic unit hydrograph based on known physical characteristics of
the basin. In this method, the peak discharge QPR, in m3/s, was
computed as
QPR=qPR*CA*AR
where qPR
is the peak discharge per square km of the drainage area due to 1 cm of
effective rainfall for rainfall duration of tr
in m3/s/sq. km., CA
is an aerial reduction factor that accounts for the fact that the average
rainfall intensity over a large area is smaller than that over a small area, R is the rainfall in cm for duration tR derived from the 24-hour
rainfall with the reduction for area. For use qPRshall be computed from the relation
qPR=2.78*
Where CP
is a coefficient depending upon basin characteristics and tPR is the lag time in hours for rainfall duration tR, calculated as
tPR=tPR+0.25*(tR-tr)
In the above equation, tr
is the standard duration of effective rainfall in hours given by
Tr=
And tpr
is the lag time from the midpoint of effective rainfall of duration tr to the peak of a unit
hydrograph in hours, computed as
tPR=0.75Ct*(LLc)0.3
Where Ct
is a coefficient depending upon basin characteristics, L is the length of stream from the station to the upstream limit of
the drainage area in km and Lc
is the distance along the main stream from the basin outlet to a point on the
stream which is nearest to the centroid of the basin in km. The coefficients Ct and CP shall be determined from analysis of some known
hydrographs in the region. In the absence of hydrographs, the values of Ct and CP may be adopted as 1.5 and
0.62, respectively.
4.7.2.1.2.2
B.D. Richard’s Method
B. D. Richard‟s method was used for flood estimation using
rainfall and basin characteristics. The method consists of computing the flood
discharge Q in m3/s using the equation. Q = 0.222AIF Where A is
basin area in sq. km.,
I is the rainfall
intensity corresponding to the time of concentration Tc and F is an
aerial reduction factor given by
F =1.09352- 0.6628ln(A)
The value of I
shall be estimated through an iterative procedure in which an initial value of Tc in hours shall be assumed
and the following computations performed in sequence:
D=1.102*F
RTC=0.22127RTTe0.476577
I=
KR=0.65I(Te+1)
CKR=
Te3=DCKR
Te2=()*1/2.17608
Where L is the
basin length in km, S is the basin
slope, RT is the 24 hour
rainfall for return period T in mm
and Tc2 is the
second estimate of the time of concentration. The iterations shall be repeated
with Tc = Tc2 till the
difference between the assumed Tc and
the resulting second estimate Tc2
is less than 5%.
4.7.2.1.2.3
Modified Dicken’s Method
Using Dicken‟s method, the T year Flood discharge QT in m3/s shall be determined as
QT =CT A0.7
Where A is the total basin area in km2 and CT
the modified Dicken‟s constant proposed by the Irrigation Research
Institute, Roorkee, India, based on frequency studies on Himalayan rivers. This
constant shall be computed as
+4
p =100(
where a is the perpetual snow area in km2 and T
is return period in years.
4.7.2.1.2.4
Fuller’s Method
Although developed for basins in the United States of
America, Fuller‟s may be used to estimate food discharges in the ungauged
basins of Nepal for comparisons purposes. Using this method, the maximum
instantaneous flood discharge Qmax in m3/s shall be
estimated as :
Q
Where QT is the maximum 24 hour flood with
frequency once in T years in m3/s and A is the basin area in sq. km.
QT shall be given by :
QT = Qav
In which Qav is the yearly average 24 hour flood
over a number of years , in m3/s ,given by
Qav=CfA0.8Where Cfis Fuller‟s
coefficient varying between 0.18 to 1.88. For Nepal, Cf may be taken
as the average of those values, i.e. equal to 1.03 .
4.7.2.2
For Gauged River Basin (GRB):
4.7.2.2.1.1
Gumbel’s Method:
This extreme value distribution was introduced by Gumbel
(1914) and is commonly known as Gumbel‟s distribution. It is one of the most
widely used probability- distribution functions for extreme values in
hydrologic and meteorological studies for prediction of flood peaks, maximum
rainfalls, maximum wind speed, etc.
Gumbel defined a flood as the largest of the 365 daily flows
and the annual series of flood flows constitute a series of largest values of
flows. According to his theory of extreme events, the probability of occurrence
of an event equal to or larger than a value of x0
P(X≥x0)=1-
In which y is a dimensionless variable given by
y=a(x-a)
a=
Thus
Y=
Where = mean and
x= standard deviation of the variate X. In practice it is the value of X for a given P that is required and the eqn. is transposed as
Yp=-
Noting that return period T=1/P and designating YT=
the value of y, commonly called the reduced variate, for a given T,
YT=-[
YT=-[0.834+2.303
So, the value of variate X with a return period T is
XT=
Where,K=
Since the MadmeKhola is not a gauged river, we could not
have the provision of daily discharges of the river. So the precipitation data
of the nearest rainfall station- Chame.
The values obtained from Gumbel‟s Method are fitted on the
best fit line obtained from plotting position method.
4.7.3
Comparison of the flood of
different method
In order to calculate the flood discharges we used several
methods like – Regional methods such as WECS and Rational, empirical methods
such as Snyder, B D Richards, Fuller and Modified Dickens methods. Similarly
Gumbel‟s method was used to calculate the maximum rainfall for different return
periods. So obtained value of maximum rainfall were used in Snyder‟s method and
B. D. Richards method to calculate the flood discharges. Since the catchment
area is small i.e. only 36.28 sq.km, the time of concentration is very small
than the duration of rainfall. So, Gumble method gives the correct values of
high flood. Therefore,
the flood discharge given by Gumble Method will be used for
the design purpose which is in the higher range than the values obtained from
other method fulfilling the criteria for the design purpose.
Table 7:Comparasion of Flood
Discharge
Fig 8: Comparison Of Flood Flow Analysis
5
PROJECT
DESCRIPTION
5.1
Project layout
The Madme Khola
Hydropower Project is a simple run-of-river scheme. The headwork site is proposed
to be located in Namarjung Lower Municiplaity. This scheme diverts Madme
khola using weir through a 2130.42m long
headrace canal and 490 m penstock pipe to the powerhouse. Being a medium
discharge-low head project, the powerhouse will accommodate two units of
Francis turbines having a total installed capacity of 3.14 MW. The water from
the tailrace will be released again to Madme Khola.
5.2
Design of hydraulic structures
5.2.1
Weir and Undersluice
In order to divert the design discharge through intake, a
structure (i.e. Weir) is constructed across the river to obstruct the natural
flow of water and raise the water level in the upstream. With the provision of
undersluice the bed loads are safely flushed to the downstream without
interrupting the flow through the intake. Guide walls of concrete, masonry and
rip rap is constructed in both upstream as well as downstream to protect the
erosion of the banks as well as to constrict the flow of the water in the
river. Also to prevent the scouring of the river bed concrete aprons along with
boulder rip rap are used in upstream as well as downstream.
Selection
of Weir Type
Among the different types
of weirs, Ogee type weir is used since it has highest value of the discharge
coefficient and has practical shape of water so aeration and air entrapment is
prevented thus avoiding cavitation.
5.2.1.1
Design Consideration of Diversion Weir
The design of weir includes computing the elevation of weir
crest, length of weir, computing the forces acting on the weir and checking the
safety of the weir from all aspects like overturning, sliding, crushing etc.
They all are explained in the following articles.
Elevation of Weir Crest
There are various factors that affect the elevation of the
crest; since diversion of water is the purpose in this case thus the height of
the weir should be sufficient to pond the water at a level that can facilitate
design flow in the intake. Thus the height of the weir is governed by the
height of intake sill, depth of intake orifice and depth of the river at the
intake site.
The bed level of the river is 2881 masl. The crest level of
the weir is provided at an elevation of 2883.6 and the crest level of the
undersluice is 2881.
Length
of the weir and Undersluice
The length of the weir depends upon the width of the
waterway at the intake site. Crest length should be taken as the average wetted
width during the flood. The upstream and the downstream should be properly
examined for the protection consideration.
Rise in water level on the upstream of the structure
after construction of the weir is called afflux. Fixation of afflux depends on
the topographic and geomorphic factors. A high afflux shortens the length of
the weir but increases the cost of the river training and protection works. For
alluvial reaches it is generally restricted to 1m but for mountainous region it
may be high. The waterway must be sufficient to pass the high flood with
desired afflux. The water way is calculated by the lacey's perimeter formula:
p=4.75(Q)0.5
for alluvial channel. But for boulder reaches it may be taken just as 60%
of “p” calculated above. Minimum waterway is taken as actual width available
between riverbanks.
5.2.1.2
Forces acting on weir
The main forces acting on the weir when it is in
operation are: water pressure, uplift pressure, silt pressure and weight of the
weir.
5.2.1.2.1
Water pressure
It is the major external force acting on the weir. This is
called hydrostatic pressure force and acts perpendicular on the surface of the
weir and its magnitude is given by
P=0.5xyxH2Xb
Where,
y=unit weight of water
H= depth of water
b= width of
the weir surface
This pressure
acts on H/3 from the base.
5.2.1.2.2
Uplift pressure
Water seeping thought the pores, cracks and fissure of the
foundation material, seeping through the weir body itself and seepage from the
bottom joint between the weir and its foundation exerts an uplift pressure on
the base of the weir. The uplift pressure virtually reduces the downward weight
of the weir hence acts against the dam stability. Uplift pressure is considered
during stability analysis.
5.2.1.2.3
Silt pressure
The silt gets deposited on the upstream of the weir and
exerts the horizontal and vertical pressure as exerted by the water. So
flushing of the silt should be dined regularly to reduce its effect of
destabilizing the weir. It is done by use of undesluice gate. The silt pressure
is given by the following relation;
Psilt = 0.5*Ysub*H*Ka
Where,
Ysub=Submerged unit weight of silt,
H=Depth of silt deposited and
Ka =
Coefficient of Active earth pressure
= (1 - SinØ)/(1+ SinØ).
Ø = Angle of internal friction of silt
The silt
pressure force also acts at a height of H/3 from the base.
But for
practical considerations, equivalent Liquid = Mix of silt and water
Yliquid (v)=
1950kgf/m3
Yliquido(h);=1360kgf/m3
5.2.1.2.4
Weight of Weir
The weight of weir and its foundation is the major stabilizing,
resisting force. While calculating the weight, the cross section is spitted
into rectangle and triangle. The weight of each element along with their C.G.
is determined. The resultant of all three force will represent the total weight
of dam acting at the C.G. of dam, when the sectional area of each part is
multiplied by unit weight of concrete weight. The weir is designed with ogee
profile for spilling over its length. Hence weight is calculated by knowing its
section and multiplying by its unit weight.
5.2.1.2.5
Protection Work for Weir Structure
The weir should be well protected from the flowing river to
avoid creep effect. For this the wing wall is essential to construct. It should
be well anchored into the bed. Similarly to protect the channel bed from being
eroded, launching apron is used. To protect the weir body riprap is usually
placed. In the site both the banks are rocky hence not any especial protection
shall be introduced. Some sorts of works to protect banks and to confine the
river at upstream mat be requires. Gabion walls are used as protection works
for the banks which ultimately protect the degradation of the weir. In the
downstream side of the spillway energy dissipater is designed to the excessive
energy of the flood water. Divide wall is constructed to prevent the cross flow
of the weir spillway portion and the undersluice portion. The undersluiced
portion is designed as for the flood flow with limited opening of maximum 3m
and energy dissipater as the submerge flow. To prevent the seepage effect,
shear piles are inserted at the upstream and downstream.
5.3
HEADWORKS
The headworks layout has been selected considering the
topography, geological conditions, space needed and flow pattern in the river.
Besides, the project has been designed in consideration with efficient
operation during all normal situations.
The headworks
design of the project has been based on the following principles.
·
The structures will be able to divert
necessary flow into the system
·
Bed
load entry to intake is negligible and mostly passed through undersluice
·
Structures will be safe from any hazardous floods and
excess flood in the river will be safely passed to downstream through ungated
and uncontrolled free flow spillway.
·
Any
floating debris will not choke the intake and will safely pass to downstream
The design basis of each of the structure of the project is discussed
below.
5.4
DIVERSION WEIR
The diversion
weir consists of an uncontrolled ogee shaped concrete overflow weir having a
length of 8.85m. The crest level has been fixed at an elevation 2883.6masl. The
head over the crest has been calculated by using the weir formula.
Q = Cx LxH2/3
Where,
C = weir
discharge coefficient and assumed 2.210 for ogee profile weir
L = weir length in meters
H = flow
depth over crest in meters
The diversion
weir is designed to pass 1 in 100 years flood, which is estimated to be 46 m3/s.
The flood water level for 100 years flood at the weir area has been determined
assuming that the flushing gates remain closed due to operating failure. The
flood level during such condition will be at 2885.124 masl.
In principle,
the under sluice gates shall be fully open during monsoon period and the water
head above the weir crest will be always less than that mentioned above. During
the monsoon period the river transports heavy bed load, which will erode the
concrete surface. Concrete surface. Therefore, hard stone lining has been
proposed to prevent concrete erosion at end of ogee surface.
5.5
ENERGY DISSIPATION AT DOWNSTREAM
A hydraulic jump stilling basin at the downstream of the
weir with a combination of
boulder lined bed is proposed for the energy dissipation.
The length of the stilling basin will be 11.6 m. Boulders of size 0.2 to 0.8 m
diameter have been provisioned.
5.6
UNDERSLUICE
One under sluice opening having of 1.5 wide has been
designed to prevent bedload entering the intake and possible build up of the
bedload in front of the intake. For controlling flow through the under sluice,
one hydraulic gate has been provisioned. The under sluice has been designed
with the characteristics given below:
·
Maintain a guided and uniform flow in front of
the intake.
·
Enable the intake
to draw desired discharge during normal flow in the river with no or
insignificant suspended sediments.
·
Scour and sluice
the sediment deposited in front of the intake.
·
Pass the part of the high flood during monsoon.
Maximum discharge through submerged undersluice orifice for
the design flood of 100 years return period in the river has been calculated
the using following relationship and the details of the calculation are given
below.
Q= CxAx 2x9.81x
Hmax
Where,
C =
Coefficient equivalent to 0.6
H =
Effective head over the orifice in meter
A =
Opening area in square meters
5.7
INTAKE
An orifice tvpe side intake has been designed to divert
design discharge of 2.81m3/sec and 20-30% additional discharge
required to flush the sediment from the gravel flushing and settling basins. In
total, the design discharge for the intake will be 3.65m/sec. The intake
consists of 2 orifices of size 2 m wide x 1 m high. As a coarse trash rack, a
net made of iron pipe is proposed to cover the orifices so that boulder gravel
of larger size will not enter through the orifices.
5.8
TRASH RACK
Trash rack shall be provided at the intake entrance to
prevent the entry of any trash, such as grass, leaves, trees, bushes, timber,
suspended sediments or rolling runner, boulders, which would not pass easily
through the smallest opening in the turbine runner.
5.8.1
Hydraulic Design of Trash racks
The hydraulic design of trash racks shall consist of
determining the shape of the
Trash rack structure, inclination of rack and geometry of
rack bars.
5.8.2
Shape of Trash Rack Structure
The shape of the trash rack structure shall be chosen to
meet the requirements of the head works layout and head losses. Generally, a
straight trash rack structure shall be adopted for ease of construction,
5.8.3
Inclination of Racks
The inclination of racks shall be fixed based on practical
consideration related to the raking operation. Except for guided racks, racks
shall be installed in a slight inclination so that trash does not roll along
the rack during upward raking. For manual raking, the slope shall be 1 vertical to 0.33 or 0.55
horizontal. Where mechanical raking arrangement is provided, the slope of the
racks shall be kept at 10 to 15 degrees with the vertical unless otherwise
specified by the manufacturer of the raking equipment
5.8.4
Rack Velocity
The velocity of flow through the rack structure shall be
limited to 1 m/s for small units closely set rack bars or at intakes where
raking is provided. A velocity up to 1.5 m/s shall be permitted at large units
with wider spacing of rack bars and where mechanical cleaning of rack is
provided a velocity of 1m/s was passed through the designed trash rack,
5.8.5
Rack Bar Geometry
From hydraulic consideration, a streamlined rounded and
tapered rack bar shall be desirable. However, considering the higher cost of
these bars and possibly of jamming of trash between them, simple rectangular
bar type racks may normally be used, provided such bars don't result in excess
head losses.
5.8.6
Losses at Trash Packs and intake openings
Head loss at intake opening should be calculated from the
formula
hr=k*(V2/2g)
Where,
k = entrance loss coefficient in m.
V = Velocity of flow through trash rack, computed on grosse
area in m2
g= acceleration due to gravity in m/s2
And,
the head losses at the trash rack has been computed using the following formula:
hr
= K* (t/b)*(V2/2g) *sin
Where,
h
= loss of head through racks
t
= thickness of rack bars
b
= clear spacing between rack bars
V = velocity
of the flow through trash rack, computed in gross area
= angle of bar inclination to the horizontal
K
= factor depending on bar shape
5.8.7
Structural Design
General
Arrangement
The trash racks shall generally consist of equally spaced vertical
bars supported on horizontal members sitting in the grooves of piers. The size
of each trash rack unit shall be proportioned from consideration of
hoisting/lifting capacity.
Spacing of Trash
Bars
The clear spacing of the vertical rack bar shall generaly be
5mm less than minimum opening in the turbine runner blade or wicket gates. It
may vary between 10 to 100mm. In general, a close spacing shall be adopted for
small turbines while a wider spacing shall be preferred for larger ones 100 mm
trash bars spacing was provided in our design
The spacing of horizontal members of the trash rack lies
between 400 to 500. The spacing shall ensure that the laterally unsupported
length of trash rack bar does not exceed 70 times the bar thickness.
Bar Dimension
The thickness of trash bars shall not be less than 8 mm. For
deep submerged racks, the minimum thickness shall be kept 12 mm. The depth of
trash bar shall not be more than 12 times its thickness and nor less than 50
mm.100 mm thick bar was used in our design
5.9
GRAVEL TRAP
5.9.1
General
Gravel trap, as the name denotes are designed to trap gravel
that enters the intake along with the diverted flow. The structure is not
required if a river only carries fine sediments and not gravel (even during
floods). However, most mountain rivers in Nepal carry gravel, especially during
floods. In the absence of gravel trap, gravel will settle along the gentler
section of headrace or in the settling basin, where it is difficult to flush
out.
The following criteria should be used for design of gravel
trap
·
The gravel trap should be able to trap particles
larger than 2mm diameter and the velocity in the gravel trap should be limited
to 0.6m/s.
.
·
If the gravel trap is hopper shaped, the floor
slope should be about 30degree (1:1.7). Such an arrangement will facilitate
easy flushing of gravel. If it is not possible to construct such a shape, the
floor should slope towards the flushing end, with a longitudinal slope of 2-5%
·
The length of gravel trap should be at least 3
times the width of the headrace canal or 2m, whichever is larger. With this
fixed length and a velocity of 6m/s. the required width of the trap can be now
determined.
·
To minimize blockage of headrace or damage due
to abrasion in the headrace, gravel trap should be located as close to the
intake as possible.
Gravel trap can be emptied via flushing gates or by lifting
stop logs (i.e. wooden planks). Since, gravel enters the intake only during the
high flow, incorporating stop logs is generally more convenient and more financial.
5.9.2
Hydraulic Design
Fall
velocity
The fall velocity shall be determined by:
W = (3.33*g*d*(S-1))^0.5 (Newtons equation)
Where,
S =
specific weight of particle
d =
particle size to be transported by flow
However, for our calculation, fall velocity (w = 0.027 m/s)
has been determined using fall velocity graph presented in ITDG manual
Critical velocity
For the size of gravel to be transported by the flow in the
gravel trap, the critical velocity of flow shall be determined by camp equation
which is as follows.
Vcr = a (d)^0.5
Where,
Vcr is
the velocity of flow, cm/sec and in our calculation Vcr = 0.20m/s.
a = 44 for particle size greater than 1mm.
d = 0.20 mm = Particle size to be transported by flow
Area of gravel trap
To trap the particle size of
above 2 mm diameter, the velocity in the gravel trap should be limited to 0.6
m/s.
Area of gravel trap, A = Q/V
Where,
Q = design discharge +
flushing discharge = 3.65 m3/s
V = 0.6 m/s
A = 45 m2
Length of gravel trap
B = Width of gravel trap = 3
m
Thus, obtained length=5 m
Protection Work
Gates are used to control the flow across the gravel control
the flow across the gravel trap. Flushing gates are used to flush the settled
matter. The flushing orifice is controlled using the flushing gates. Flushed
water and excess water are safely diverted to the river using open channel. The
site protection work, fencing, etc. is carried out.
5.10
SETTLING BASIN
5.10.1
General
The suspended particles entered in a canal, if allowed to
flow through the penstock pipe and turbine, cause abrasion of such units and
reduce efficiency as well as durability. In addition, problem of clogging is
always present due to such particles in turbine units. There is also the
possibility of siltation in canals. So, the finer particles escape from gravel
traps are to be removed before entering into penstock. The suspended sediments
that are not settled in the gravel trap are trapped in the settling basin. The
basic principle of settling is that greater the basin surface area and lower
the flow velocity, the smaller particles can settle. A settling basin has
significant larger cross sectional area than the headrace canal and therefore,
flow velocity is lower which allows the settling of suspended materials.
A Settling basin must satisfy the following criteria:
5.10.2
Settling capacity
The length and the width of the basin must be large enough
to allow a large percentage of the fine sediments to fall out of the suspension
and be deposited on the bed. The sediment concentration passing the basin
should be within the acceptable limits. The geometry of inlet, the width of the
basin and any curvature must be such as to cause minimum turbulence, which
might impair the efficiency.
5.10.3
Storage capacity
The basin should be able to store the settled particles for
some time unless it is designed for continuous flushing. Continuous flushing
mechanisms are however not incorporated in micro hydro schemes due to
complexity of design and the scarcity of water
during the low flow season. Hence, the storage capacity must be sufficiently
large that a basin does not require frequent flushing.
5.10.4
Flushing Capacity
The basin should be able to be operated so as to remove the
stored particles from it. This is done by opening the gates or valves and
flushing the sediments along with the incoming flow in the basin. The bed
gradient must be steep enough to create velocity capable of removing all the
sediments during flushing.
5.10.5
Components of Settling Basin
The settling basin has three distinct zones: the inlet,
settling zone and outer zones
Inlet zone
This is the initial slope where the transition from the
approach canal to the settling basin occurs and is a gradual expansion in the
basin and 1 in 5 slope was provided.
Settling
zone
The basin reaches the required width at the beginning
of this zone. Particles are settled, stored and flushed in this zone. The
length of this zone is longer than the inlet or the outlet zones. It should be
noted that long narrow basins perform better than short wide basins. A range of
4 to 10 is recommended for the ratio of the length to width (L/B). The length of
settling basin obtained is 51.37m and width is 6.42 m of each chamber. We have
used two chamber. So L/B ratio is 8 which is within the permissible limit of 4
to 10 and the length of outlet zone was found to be 4.92 m.
Outlet zone
This forms the transition from the settling zone to the
headrace canal and then to the headrace canal again. The transition can be more
abrupt than the inlet expansion
5.10.6
Design consideration
The settling basin is designed following standard practices.
Particle approach is used to design it. Trap efficiency is selected as 90%
removal of 0.2 mm sized sedimentary particles. Vetter's equation is used for efficiency
calculation. Camp's equation and various charts
are used to compute the transit velocity and the settling velocity.
5.10.7
Protection work
Gates are used to
control the flow across the settling basin. Flushing gates are used to flush
the settled matters. The flushing orifices are controlled using the flushing gates.
Flushed water and the excess water are safely diverted to the river using open
channel. The side protection work like fencing etc. are carried out.
5.11
Penstock
5.11.1
Pipe Material
In this study, three types of pipe material were
identified as alternatives for the Pipe Material penstock and are:
·
Steel
·
Ductile iron
·
Glass reinforced
plastic(GRP)
Steel pipes are locally made in Nepal. For an above ground
arrangement, it provides the required durability. Additionally it is lighter
than the ductile iron option and is not susceptible to vandalism as the GRP
option.
Ductile iron with an internal cement mortar lining is
another option for the penstock. Compared to steel, this option is suitable if the
penstock has to be underground as it less vulnerable to corrosion. But it is
heavier and the transportation and the installation are more onerous, hence is
not considered further in this study.
The GRP pipe is relatively light and has a smoother bore. But
for an above ground arrangement, it is extremely vulnerable to vandalism as it
is susceptible to impact loads. Therefore steel option is selected.
5.11.2
Penstock Arrangement
The penstock starts at an elevation of 2877.5m, passes
through the powerhouse and terminates at the connection to the turbine at an
elevation of 2748.8 m. The penstock has 1100 mm internal diameter steel pipe.
The total length of the penstock
is approximately 490 m. After
placing and aligning, the sections will be welded at site.The penstock is
exposed (above ground) and is supported on a series of anchor blocks and piers.
Because of the topography and the landmarks, the alignment requires 6 vertical
bends. In addition, vertical bends along the alignment minimize excavation and
the height of the support piers.
The pipe wall thickness remains 12
mm throughout the length. Thick thickness is such that it withstands the surge
pressure. The surges should be investigated further in conjunction with the
electromechanically design during the detailed design phase. The penstock is
provided with an expansion joint immediately below each anchor block.
5.11.3
Anchor Blocks
Anchor blocks are provided at the bends along the alignment.
Additional anchor blocks are provided in straight reaches where the sectional length
exceeds the maximum allowed for expansion.
The bends along the alignment is only one type that is
·
Vertical bends
·
Combined (horizontal and vertical) bends. But in
our design there is no combine bend.
·
There are 6 vertical bends. The size of the
anchor blocks depends on the combine bend. Angle of the bend, the hydrostatic
pressure and the topography.
Anchor blocks are of concrete with 40% plums and nominal
reinforcement to avoid uneven settlement & cracking. The blocks have been
designed to provide stability against sliding, overturning and bearing
pressure.
An anchor block is designed for most critical bend condition.
5.11.4
Support plers
The penstock pipe rests on a series of support provided
uniformly in the sections between anchor blocks. To avoid overstressing the
penstock pipes the spacing is maintained at not more than 6m-10m. There are 65
support piers in total.
Support piers are of stone masonry with a 1:4 cement mortar.
The size and shape of the piers depend upon the topography. The piers have been
designed to provide stability against sliding, overturning, and bearing
pressure,
5.11.5
Expansion joints
Expansion joints are provided along alignment within
the downstream side or upstream side of the anchor blocks. The expansion joints
will be of sliding type.
These allow the penstock pipes between two anchor blocks to
expand and contract with varying temperature.
6.14.6 Corrosion protection
To prevent corrosion, the penstock must be painted
with two caps of 300um epoxy paint and single coat of zinc chrome primer.
5.12
POWER HOUSE
5.12.1
General
The Powerhouse
accommodates electro-magnetic equipment such as turbine, generator,
agro-processing units and control panels. The main function of building is to
protect the electro-magnetic equipment from adverse weather as well as possible
mishandling by unauthorized persons. The powerhouses is governed by the
penstock should have adequate space such that all equipment can fit in and be
accessed without difficulty. Cost can be brought down if the construction is
similar to other houses in the community.
The generator turbines
and the belt drives need to be securely fixed on the machine poundation in the
powerhouse. This requires a careful design since the equipment generates
dynamic force and even a slight displacement can cause excessive stress on the
various parts of the equipment and lead to equipment malfunction.
5.12.2
Location of Powerhouse
The location of powerhouse is governed by the penstock
alignment since the building must be located at the end of penstock. Apart from
this, the following criteria are recommended for locating the powerhouse.
·
The powerhouse should be safe from not only
annual floods but also rare flood events. Discussions
should be held with the local community members to
ensure that floodwaters have not reached the proposed powerhouse site within at
least the past 20 years. For micro-hydro schemes of 50-100 KW it is recommended
that the powerhouse be above the 50-year flood level.
·
It should be possible to discharge the tail
water safely from the powerhouse back to the stream
·
If possible the powerhouse should be located on
level ground to minimize excavation work
·
The proposed location should be accessible
throughout the year.
·
At some place this may require constructing a
new foot trail
·
The powerhouse should be located close to the
community that it services, provided that the penstock alignment and other parameters
are feasible and financial. This will reduce the transmission line cost, and if
agro-processing units are also installed in the powerhouse, the community will
not have to carry their grain for a long distance.
5.12.3
Length of machine hall
Length of machine hall depends upon the summation of
length of number of units and one service/repair bay. Usually the length of 1
unit is fixed equal to the 4D+2.5 m, where D is the diameter of the turbine and
2.5 m is extra clearance provided. The estimated length of machine hall is 18 m.
5.12.4
Height of machine hall
Height of the powerhouse depends upon the height clearance
from the ground to the lifting object through the
crane, maximum size of plant machinery (Turbine or rotor of the generator),
depth of the girder and the crane system, etc.
5.12.5
Tailrace
Tailrace is the final civil structure that coveys the design
flow from powerhouse the river where it is disposed off. Open channels or pipes
can be as tailrace structure. Often adequate at, such attention is not given to
the design and Construction of the tailrace, probably because it does not
affect power production seriously. However, such a practice can result inadequate
depth of the tailrace of the tailrace pit or erosion of slopes that could
threaten the powerhouse structure. The designed dimension of tailrace canal is
1.5m x 1m (BxH).
Mechanical Units
A hydropower plant requires a great deal of mechanical and electrical
equipment. The major electrical components are: Shaft, bearing couple, etc for
generators, oil circuits and pumps, compressors and air ducts, braking equipment.
The arrangements for lighting, water supply and drainage should also be
provided.
Turbine
Turbines are machines, which convert kinetic energy into
mechanical energy and transmit it to the generator through direct coupling of
shaft to it that it in turns converts mechanical energy into electrical energy.
Based on the energy conversion, turbines are classified as Impulsive or Active
and Reactive turbines.
I.
Impulse turbine
The turbine, in which pressure head or potential energy of
water is converted into kinetic energy of water in the form of jet of water
issuing from one or more nozzles and hitting a series of buckets mounted on the
periphery of the wheel, at atmospheric pressure is called impulsive turbine. It
is used for high head and low discharge. Pelton is the example of impulse
turbine.
II Reactive
turbine
The turbine, in which pressure head or potential
energy of water is utilized to rotate the runner or the turbine is called the
reactive turbine. The water flows through the runner under kinetic and
potential energy. The turbine runner is submerged and water enters all around periphery
of the runner. Water is taken up to the tailrace by means of a closed draft
tube and thus whole passage of water is totally enclosed. Francis, Kaplan,
Propeller, Deriaz turbine etc are the examples of reactive turbines.
Design Philosophy
There are various types of turbines with wide hydraulic
features, Selection of suitable type of turbine for the project depends upon
several factors like head, discharge, power production, load condition and
corresponding efficiency, quality of Water, bar level size, construction
feasibility, etc. Selection of turbine is essential for me layout of the
powerhouse, approaching the discharge pipes, conditions construction and
exploitation and techno Financial parameters.The turbine selected from
following basic criteria:
1) Head and
Discharge
Medium head and low discharge -Pelton turbine
Medium head and medium discharge -Francis turbine
Low head and High
discharge - Kaplan
turbine
2) Specific
speed
10 to 50 - Pelton turbine
80 to 400 - Francis
300 to 500 - Kaplan (diagonal)
450 to 1200 - Kaplan (Axial)
Different
literatures had given various charts/graphs for the selection of turbine. For medium
high to medium and low heads and normal quality of water, Francis turbine is
suitable. Turbine is designed based on the specific speed (Ns), which is the
speed of the geometrically similar (identical in shape, blade angles, gate
specific speed between 60 to 400 rpm, Francis turbine is suitable. Since,
reaction turbine is susceptible to cavitation, setting of turbine is made based
on the cavitation criteria. A draft tube is always provided with the reaction
turbine to receive the pressure head at the outlet of the turbine. Efficiency
of the Francis turbine decreases substantially at part load operation. For run
off river plants, discharge of the river becomes lower than the design
discharge of the plant. So, part load operation is essential. If a Francis
turbine is allowed to run at part load for long time, cavitation become more
serious. Thus, these criteria should be kept in mind while designing the
turbine.
Figure 09: Turbine selection graph
Considering two turbine units with net head of 126.7 m and 2.21
m3/s and 0.6 m3/s design
flow for two diiferent unit, with respect to the turbine selection graph, the
best suitable turbine is found to be of Francis Turbine. Hence, for the study
Francis Turbine is adopted.
Generator
Usually in hydropower generator, armature is formed at the
stator and poles are formed at the rotor. The high voltage current is tapped
from the stator and connected to the transformer through the insulating cable
The stator is the steel frame of the laminate construction
serving as the magnetic core and inside the slut armature winding is lad. The
insulation of the stator is achieved through the resin impregnated soaked) mica
paper, which can withstand manufactured in number of segments and Temperature
upto 150°C. The stator is manufactured in the number of segment and installed
at the site.Whole the stator rest on the concrete foundation.
The rotor consists
of the frame of the race steel structure similar to the strut of the wheel.
These radial structures are radiated from the central hub and are mounted on
shaft of the generator. This assembly is called the spider The spider consist
of the steel rim covering at is periphery and consist of the slots at its
surface to form the poles of the rotor.
Rotor can be classified as:
1)
Thrust bearing type in this type the spider
assembly is on the horizontal blade and thrust of the rotor is supported at the
thrust-bearing structure located above the spider assembly.
2)
Umbrella/semi-umbrella-Umbrella type: in this
case thrust of the rotor is supported on the trust bearing structure below the
spider assembly, which is skewed as like the umbrella. if the spider is one the
horizontal plane then is termed as the semi umbrella type.
Exciter
In order to create the magnetic pole at the rotor of the
generator is required to feed it by direct current Providing of the field
current to the rotor is termed as the excitation it could be done through the
separate generator battery connected to the shaft of the turbine. After the
generation of electricity, current could be taken from the main generator
output through the step-down transformer. The alternate current is converted
into the direct current through the Thyristor
Transformer
According to the
power of the generator, the voltage of the generator is usually fixed
Upto 15MW. U=6.3 KW
Up to 70 MW. U=10.5
KW
And greater than that. U=18 KW
For the transmission
of the power to the long distance, it is required that the voltage so as to
minimize the transmission loss. For this purpose, step up is transformer provided
to increase the transmission voltage at the power plant. In case of the
underground power plant separate transformer gallery is provided and in case of
surface powerhouse, it is usually
located outside near to the generator
Switchgear
It is the system
provided at the powerhouse for the connection and breaking of the when
necessary. It consists of switches. Isolators. Surge arrestor and breaker.
Switches are provided at the generating voltage before transformer and the
transmission voltage after the transformer. Usually, the switchgear at the generated
voltage is located inside the powerhouse and for transmission Voltage located
outside and termed as outside switchyards
Control room equipments
·
TV monitoring of the different location
of power plant, hydraulic structures and their maneuvering
·
.Start and stoppage of the plant
·
Machine loading condition and frequency
control through the governor
.
·
Generator and system voltage control
·
Machine running status
Transmission line
Energy generated at the power station has to be carried to
the consumer's premises through a network of transmission and distribution
lines. Transmission lines transmit bulk electrical power from sending end
stations to receiving end stations without supplying any consumer's enroot
Transmission system of an area is known as grid The different grids are
interconnected through tie lines to form a national grid. Transmission voltages
in Nepal are 33 KV, 66 KV and 132 KV and planning to transmit at 220 KV. The
high voltage transmission lines transmit electrical power from the sending end
sub-station (Power Station) to the receiving end stations. The transmission
facilities affect the cost and reliability of energy supplied to the consumers
to a great extent.
5.13
Miscellaneous Work
River training Structures
A flood protection
wall along the river bank may be required if there is a high probability of
flood damage to the initial headrace and other structure such as gravel trap
and settling basin. Such walls are also called River Training Structures since
they confine the river channel. The wall height should be greater than or at
least equal to design flood level.
The foundation of any river training wall must be protected from undermining by
the river. This can be done by one of the following methods:
·
Founding the wall on rock or large boulders. For
gabion walls, it may be necessary to first build up a level space base using
stone masonry concrete.
·
Founding the wall below possible scour depth.
·
Using a gabion mattress along the riverside o the wall. This
method is not appropriate in
river carrying a heavy bed load, because boulders moving during floods will
damage the gabion wires.
Fencing
Various structures are to be protected from the entry of
unwanted people and cattle The area is to be separated from the cultivated
area, wire fencing is used in the project for this purpose.
Catch Drain
It is very important to prevent the entry of the surface and
subsurface water into the various components of the project. When the structure
is below the neighboring ground, there is every possibility of entry of
rainwater in the structures. So, catch drain is constructed in such areas.
6
POWER OUTPUT AND ENERGY GENERATION
6.1
POWER TYPE
6.1.1
FIRM POWER
A firm power is
(primary power) is the amount of power that a plant can deliver throughout a
year. This power is available for more than 95% of certain time period. It is a
power available when the flow of the river is minimum in run-of-river
plant. The firm power can be guaranteed
to the consumer.
6.1.2
Secondary Power
This power
available intermittently for
unpredictable time, the power is called secondary power. In other words, it is surplus or non power than the primary
one and is useful in the interconnected system of power station i.e. grid.
There is no guarantee of the secondary power and it is provided to
consumer on ‘as when available’ basis.
6.1.3
Peak power
It is the power when
its value is greater or equal to 4/3 of the mean or mid power.
6.2
TYPES OF HEAD
6.2.1
Gross head
It is the difference
in water level elevation at the point of diversion and the point of return of
water back to the river. The gross head obtained is 345 m.
6.2.2
Net Head
It is the head
obtained after the deduction of losses between diversion point and axis of
turbine from gross head. The net head obtained is 339.22 m.
6.3
OVERALL EFFICIENCY
Overall efficiency =Turbine efficiency * Generator
efficiency
Where, Turbine efficiency =85% and generator efficiency =90%
6.3.1
INSTALLED CAPACITY
The installed
capacity of a power plant is the maximum power which can be developed by all
the generators of the plant at the normal head and with full flow.
Power=9.81*2.81*126.7*0.9
=3.14 MW
Table No 8: Energy
Calculation Sheet
Net Head=126.7 m
Design Discharge=2.81 m3/sec
Dry Season Outage=5%
Wet Energy Rate (Nrs)= 7.1
Dry Energy Rate (Nrs)= 12.4
Wet Season Outage=10%
Overall Efficiency=90%
ENERGY CALCULATION SHEET
Month |
Days |
River Flow(m3/S) |
Design Flow(m3/ S) |
Dischage for energy generation (m3/S) |
Power Available( KW)Dry Season |
Power Available(K W)Wet Season |
Power after Outage(KW) Dry
Season |
Power after Outage(KW) Wet
Season |
EnergyAvailabl e(KWh)Dry Season |
EnergyAvailabl e(KWh)Wet Season |
Annual Revenue Dry Season(Nrs) |
Annual Revenue Wet
Season(Nrs) |
Remarks |
Jan |
31 |
0.74 |
2.81 |
0.6 |
671.1806 |
|
637.621551 |
|
474390.4339 |
|
5882441.381 |
|
|
Feb |
28 |
0.645 |
2.81 |
0.6 |
671.1806 |
|
637.621551 |
|
428481.6823 |
|
5313172.86 |
|
|
Mar |
31 |
0.614 |
2.81 |
0.6 |
671.1806 |
|
637.621551 |
|
474390.4339 |
|
5882441.381 |
|
|
Apr |
15 |
0.77 |
2.81 |
0.6 |
671.1806 |
|
637.621551 |
|
229543.7584 |
|
2846342.604 |
|
|
Apr |
15 |
0.77 |
2.81 |
0.6 |
|
671.18058 |
|
604.062522 |
|
217462.5079 |
|
1543983.81 |
|
May |
31 |
1.266 |
2.81 |
0.6 |
|
671.18058 |
|
604.062522 |
|
449422.5164 |
|
3190899.87 |
|
Jun |
30 |
3.103 |
2.81 |
2.81 |
|
3143.36238 |
|
2829.02614 |
|
2036898.824 |
|
14461981.7 |
|
Jul |
31 |
7.55 |
2.81 |
2.81 |
|
3143.36238 |
|
2829.02614 |
|
2104795.452 |
|
14944047.7 |
|
Aug |
31 |
8.9 |
2.81 |
2.81 |
|
3143.36238 |
|
2829.02614 |
|
2104795.452 |
|
14944047.7 |
|
Sep |
30 |
6.65 |
2.81 |
2.81 |
|
3143.36238 |
|
2829.02614 |
|
2036898.824 |
|
14461981.7 |
|
Oct |
31 |
2.738 |
2.81 |
2.21 |
|
2472.1818 |
|
2224.96362 |
|
1655372.935 |
|
11753147.8 |
|
Nov |
30 |
1.38 |
2.81 |
0.6 |
|
671.18058 |
|
604.062522 |
|
434925.0158 |
|
3087967.61 |
|
Dec(1-15) |
15 |
0.88 |
2.81 |
0.6 |
|
671.18058 |
|
604.062522 |
|
217462.5079 |
|
1543983.81 |
|
Dec(15-3 |
1 16 |
0.88 |
2.81 |
0.6 |
671.1806 |
|
637.621551 |
|
244846.6756 |
|
3036098.777 |
|
|
|
|
|
|
|
|
|
|
|
|
Revenue
in Dry season |
22960497 |
|
|
|
|
|
|
|
|
|
|
|
|
Revenue
in Wet season |
|
79932041.6 |
|
Total Energy(kwh)=13109687.02
Grand Total Income(Nrs) =
102892538.7
7
COST ESTIMATES AND FINANCIAL ANALYSIS
7.1
COST ESTIMATES AND BOQ
Compressive and
detailed estimate should be prepared for each structure that identify and
show the quantities of all work and supply items, such as excavation and fill,
concrete etc. These estimates of quantities, grouped in pay items (B O Q), will
from the basis for both the contractor to prepare their bills of payment. There
are some items the cost detail of which may be difficult to estimate and hence
their value is kept as lump sum (L. S.)
Based on the cost
estimate and other consideration, the project cost is estimated to be
48,77,56,202, NPR which is 154,236 NPR per KW.
Table No: Summary Of
project Cost
S.N |
|
DESCRIPTIONS |
AMOUNT (NRS) |
% |
|
1 |
Infrastructures development and mobilization |
|
|
|
1.1 |
Access Road |
100,000,000 |
|
|
1.2 |
Camp
facilities |
20,000,000 |
|
|
1.3 |
Water
Supply and Sanitation |
50,000,000 |
|
|
1.4 |
Mobilization
and Demobilization |
12,000,000 |
|
|
1.5 |
Construction
Power |
15,000,000 |
|
|
|
Sub-total |
197,000,000 |
40.39 |
|
|
|
|
|
|
2 |
Civil works |
|
|
|
2.1 |
Site
Clearance and Base preparation |
15,00,000 |
|
|
2.2 |
Earthwork
in excavation for foundation in boulder mix soil (riprap) |
5382395 |
|
|
2.3 |
RCC work |
7925381 |
|
|
2.4 |
PCC work |
31,220,950 |
|
|
2.5 |
Stone
soiling |
10,85,175 |
|
|
2.6 |
Bricks
masonry |
82,55,083 |
|
|
2.7 |
Brick
soiling |
11,93,520 |
|
|
2.8 |
Plastering |
29,282,481 |
|
|
2.9 |
protection
works |
1114421.56 |
|
|
2.1 |
Wooden
works |
1,90,00,000 |
|
|
2.11 |
Others |
50,000 |
|
|
|
Sub total |
74975628.76 |
15.37 |
|
3 |
Hydro-Mechanical |
|
|
|
3.1 |
Trashrack |
5,00,000 |
|
|
3.2 |
Sluice gate
( orifice,undersluice,settling basin,gravel trap) |
20,00,000 |
|
|
3.3 |
Penstock
pipe (Galvanized iron) |
28,583,660 |
|
|
|
|
|
|
|
|
Sub -total |
28,583,660 |
5.86 |
|
|
|
|
|
|
4 |
Electro Mechanical works |
89759475 |
18.40 |
|
|
|
|
|
|
5 |
Transmissionn and interconnection system
(BASE COST) |
17500000 |
3.59 |
|
|
|
|
|
6 |
Pre- development ( 2% of the base cost) |
350000 |
0.07 |
7 |
Land Purchse/lease (1.5 % of base cost ) |
262500 |
0.05 |
8 |
Environmental mitigation and monitoring cost ( 2 % of base cost ) |
350000 |
0.07 |
|
|
|
|
9 |
Contingency |
|
|
9.1 |
15 % of civil work |
11246344.31 |
|
9.2 |
10 % of hydro mechanical work |
3108366 |
|
9.3 |
10 % of electro mechanical works |
8975947.5 |
|
9.4 |
10 % of transmission and interconnection
system |
1750000 |
|
|
Subtotal |
25080657.81 |
5.14 |
|
|
|
|
10 |
VAT ( 13 % OF CIVIL WORK) |
3260485.516 |
0.67 |
11 |
Local TAX ( 1.5 % of base cost ) |
262500 |
0.05 |
12 |
Custom charge and duty ( 1 % of electro mechanical ) |
897594.75 |
0.18 |
13 |
Insurance ( 1.5 % of base cost ) |
262500 |
0.05 |
14 |
Engineering Administration and Management cost ( 5 % of base cost ) |
875000 |
0.18 |
|
|
|
|
15 |
TOTAL |
439,420,002 |
90.09 |
16 |
INTEREST DURING CONSTRUCTION |
48336200.2 |
9.91 |
17 |
TOTAL PROJECT DEVELOPMENT COST |
49,63,64,051 |
100.00 |
18 |
COST PER KW |
1,54,236 |
|
|
|
|
|
7.2
FINANCIAL ANALYSIS
Financial analysis
is a quantitative evaluation, which presents a comparison between the benefits
and cost over the lifetime of the project. The Financial analysis forms a
criterion for the selection of alternatives. Again for making the decision of
either constructing or not of the alternative, financial viability is one of
the major criteria. The revenue earned from the project has to be assessed
based on the project available energy and the anticipated rate of sales of
power. These are equated against the recurring costs, which consists mainly of
the interest on investment, depreciation of plant and equipment, operation and
maintenance expenses, to arrive at the income surpluses. No one wants to invest
for the project which will not give the good return in the future through it is
feasible technically and fruitful from regional balance point of view.
Financial analysis
is made on the value of money. Analysis may be done by calculating present
value of future cost or future value of present cost or in annuity. Generally,
following three methods are used for financial analysis.
An investment in a
small hydropower schema entails a certain number of payments, extended over the
project life, and procures some revenues also distributed over the same period.
The payments include a fixed component. The capital cost, insurance, taxes
other than the income taxes, e t c- and a variable component. Operation and
maintenance expenses- At the end of the project, in general limited by the
authorization period, the residual value will usually be positive, although
some administrative authorization demand the abandonment of all the facilities
which revert to the state. The financial analysis compares the different
possible alternative to allow the choice of the most advantage or to abandon
the project from an financial viewpoint a hydropower plant differs from a
conventional thermal plant, because its investment cost per KW is much higher
but the operating costs are extremely low, since there is no need to pay for
fuel.
The financial
analysis can be made either by including the effect of the inflation or
omitting it. Working in constant monetary value has the advantage of making the
analysis essentially independent of the inflation rate. Value judgements are
easier to make in this way because they refer to a nearby point in time which
means they are presented in a currency that has a purchasing power close to
present experience. If there are reasons to believe that certain factor will
evolve at a different rate study, the inflation was not considered
7.2.1
Methods of Financial Evaluation
When comparing the
investments of different project the easiest method is to compare the ratio of
the investment to the power installed or the ratio of the total investment to
the annual energy produced for each project. Nevertheless, this criterion does
not determine the profitability of the schemes because the revenues are not
taken into account. But constitutes criterion. The following methods are
adopted for the study.
Net
Present Value (N PV) Method
The difference
between revenues and expenses, both discounted at a fixed, periodic interest rate,
is the net present value (N PV) of the investment.
The formula for
calculating net present Value, assuming that the case flows occur at equal time
intervals and that the first cash flows occur
at the end of the first period, and subsequent cash flow occurs at the
ends of subsequent periods, is as follows
Vr=
residual value of the investment over its lifetime, whenever the lifetime of
the equipment is greater than the assumed working life of the plant (usually
due to the expiration of the legal permits).
r=periodic discount
rate (if the period is a quarters, the periodic rate will be ¼ of the annual
rate)
n=number of lifetime
periods (years, quarters, months)
Li=
investment in period i
Ri =revenues
in period i
Oi= operating costs in period i
mi =maintenance
and repair costs in period i
The calculation is
usually done for a period of thirty years, because due to the discounting
techniques used in this method, both revenues and expenses become negligible
after a large number of years. Different project may be classified in order of
decreasing N PV. Projects where N PV is negative will be rejected, since that
means their discounted benefits during the lifetime of the project are
insufficient to cover the initial costs.
Among projects with
positive N PV, the best ones will be those with greater N PV. The N PV results
are quit sensitive to the discount rate, and failure to the select the
appropriate rate may alter or even reverse the efficiency ranking of project.
Since changing the discount rate can change the outcome of the evaluation ,the
rate used should be considered carefully for a private promoter the discount
rate will be such that will allow him to choose between investing on small
hydro project or keep his saving in the bank. This discount rate, depending on
the inflation rate, usually varies between 5% and 12%. The method does not
distinguish between a projects with high investment costs promising a certain
profit, from another that produces the same profit but needs a lower
investment, as both have the same N PV.
Hence a project
requiring one million NRs in present value and promises one million one hundred
thousand NRs profit shows the same N PV as another one with a one hundred
thousand NRs investment and promises two hundred thousand NRs profit (both in present value).Both
project will show a one hundred thousand NRs N PV, but the first one requires
an investment ten times higher than the
second does.
Benefit-Cost
(B/C) ratio
The benefit-cost method
compares the present value of the plant benefits and investment on a ratio
basis. Project with a ratio of less than 1 are generally discarded.
Mathematically,
Internal Rate of Return
(IRR) Method
The internal Rate is
the discount rate r, at which the present value of the periodic benefits
(revenues less operating and maintenance costs) is equal to the present value
of the initial investment. In other words, the method calculates the rate of
return an investment is expected to yield. It can be done as
-I+(Rk-Ek)
The criterion for
selection between different alternative is normally to choose the investment
with the highest rate of return.
A process of trial and
error, whereby the net cash flow is computed for various discount rates until
its value is reduced to zero, usually calculates the rate of the return.
Electronic spreadsheets use a series of approximations to calculate the
internal rate of return.
Under certain
circumstances there may be either no rate -of-return solution or multiple
solutions. An example of the type of investment that gives rise to multiple
solution is one characterized by a net benefit stream, which is first negative,
then positive and finally negative again.
7.2.2
Result of Financial analysis
The following are
considered for the financial analysis.
Project cost (Mill
NPR) =4,963
O & M cost
(p.a.) =1.50%
Installed Capacity
(M W) =3.14
Wet season Energy
(KWH) =11258034.04
Dry season Energy (KWH)
=1851652.984
Wet Energy rate
(NPR/KWH) = 7.1
Dry Energy rate
(NPR/KWh) =12.4
Interest rate =11 %
Construction Distribution Schedule Year 1 30% Year 1 45% Year 3 25% |
Results:
Net present Value
(NPV, Mill. NPR) =323
Internal rate of
return (IRR) =20.20
Benefit Cost Ratio
(B/C ratio) =1.507
8
PROJECT PLANNING AND SCHEDULING
8.1
GENERAL
Project generates itself from ideas, which must be
technically feasible, economically viable, politically suitable and socially
acceptable. With the increasing complexity of larger projects, necessary for
better planning, and scheduling is increasing. For the success any project it
is necessary that the objectives and time schedules should be define with
reference to attainable target into account all the problems and difficulties
which may be existing at the time of drawing up of the plan or during the
course of construction period. The proper planning of any project is essential
to achieve the real goal.
8.2
PLANNING
Planning is general is the process of establishing project
goals and the ways of achieving the goals. It is a predetermined course of
action to be taken in future. Project planning is a decision planning must be
systematic, flexible enough to handle unique activities. Comprehensive project
planning covers the following areas.
·
Planning the project work
·
Planning the human resources and organization
·
Planning the financial resources
·
Planning the information system
Planning aims at achieving the project completion, making
the most effective use of time and recourse. Project planning requires both the
operational and strategic thinking and decision making. It is characterized by
creativity, innovation and ability to think rationally and prospectively,
project planning is a multistage process and enumerated as:
·
Establishment of objectives
·
Identify the key factors of the project
·
Identification of key Elements of projects
·
Establishing the logical sequencing of
activities
·
Identification of time and resources
·
Assignment of responsibilities
·
Finalize project plan
For the successful run of the project, Certain development
such as access road, temporary camps, facilities for drinking water, light
should be provided on the project site before the actual construction starts.
The construction work should be started after enough operation are lined up and
definite commitments are made for arrival of material and equipments
8.3
PHASE OF CONSTRUCTION
In the hydropower construction, the hydropower plant
construction only is not solely a project work. Before the construction of the
power plant, infrastructure required for the project such as access road,
bridge, temporary camps for works etc should be developed. These all works
should be scheduled and proceed on phase wise. General phase of project
construction can be summarized as:
·
Access road construction
·
Construction of camp
·
Construction of all civil works
·
Electromechanical works
8.4
TIME MANAGEMENT IN PROJECT
Time management simply means to get more in less time. It
means utilizing minimum time to accomplish the goals. Time is scarce resource
in project management. Time wastage means cost escalation.
8.5
PROJECT SCHEDULING
The project scheduling is the done immediately after
planning work is completed, approved, the budget estimate is prepared and the
detailed design, tendering and the master plan is more or less finalized. The
schedule of the construction works is a very important aspect of the project sa
it ensures not only the timely completion of the project to comply with the
energy requirements of the nation but alsoto have a tentative idea on the cash
flow patterns of the project. The management of finance as will as other
resources like equipments, material, and manpower for the project
implementation largely depends on the schedule of construction.
While scheduling the project, the project activities are
identified and their proper technological sequences and the anticipated time
duration for each of the activities are estimated.
Due to the innumerable activities interdependent on another
in the project, it is necessary to make the schedule in a systematic way for
easy understanding and reference. The widely used techniques are;
·
Bar chart
·
Network
analysis
9
CONCLUSION AND
RECOMMENDATION
9.1
CONCLUSION
Based on the pre-feasibility study of the
Madme hydropower project, the followings are conclude:
·
The project is technically feasible.
·
The project has
gross head of 128.7 meter and utilizes the design discharge of 2.81 m3/s
·
The installed capacity of the project is 3.14 MW
and is capable of generating 13.10 GWh net energy annually among which 1.815 Gwh
is during the dry season and 11.25 Gwh is during the wet season.
·
The project comprises two units of Francis
Turbine with one for maintenance purposes
·
The project cost is estimated to be 4,963
Million NPR which results 154,236 NPR per kilowatt
·
The project is financially feasible with the dry
energy rate of NPR 12.40/KWH and wet energy rate of NPR 7.10 KWH , the project
financial internal rate of return of the project is 20.20% and B/C ration of
1.507
9.2
RECOMMENDATIONS
For further analysis of the project at detailed feasibility
level , the following studies and
explorations are necessary.
·
Detailed topography mapping of the headworks ,
penstock alignment and powerhouse area and strip survey over the headrace
canal.
·
Surface geological mapping and subsurface
geological investigations should be
carrier out at the headworks , water
way powerhouse area.
·
A physical hydraulic modeling of the headwork,
its performance in all different flow and study of their river hydrology should
be conducted to verify and validate the design.
·
Detailed Environment impact assessment has to be
carried out.
·
Continuous hydrological measurements, both low
flow and monsoon floods should be continued.
·
Suspended sediment sapling shall be carried out
during the monsoon period.
REFERENCES
·
Conveyance and Objective type Questions and
Answers on Civil Engineering-R Agor
·
Engineering Hydrology – Subramanya
·
Flow in Open Channels – Subramanya
·
Guidelines to design hydropower –J. N. Nayak
·
Hydraulic structure fourth edition-P. Novak, A
.L. B Moffat and R. Narayan.
·
Irrigation, Engineering and Hydraulic structure
– S. K Garg
·
Irrigation, water power and water resources
engineering –Dr. K. R Arora
·
Irrigation, water resources and water power- Dr.
P.N. Modi
·
Water power Engineering- M.M. Dandekar
No comments :
Post a Comment